Field Service Scheduling Operations System
Same-day service cancellations reduced from ~17% to ~9%.
Pilot Duration
6 weeks
Measurement Window
12 weeks
Status
Production
Methodology
Audit-Ready
Client Context
Solar installation and maintenance company managing 22 technicians.
Operational Problem
- —Manual scheduling created uneven technician workloads and appointment delays.
Operational Workflow
Before Deployment
- — Manual intake
- — Spreadsheet tracking
- — Delayed operational response
- — Fragmented visibility
After Deployment
- ✓ Structured intake engine
- ✓ Automated prioritisation
- ✓ System-driven routing
- ✓ Operational visibility dashboard
Deployment Timeline
Pilot
Initial deployment on scoped process.
Measurement
Tracking against baseline.
Scale
Full production rollout.
Operational Impact
Same-day cancellation rate
Improved reliability
~17%
~9%
Scheduling admin workload
Reduced coordination
~70%
~38%
Technician visits per day
Improved utilisation
3.1
3.6
Metrics measured during the first full quarter post-deployment against a four-week pre-deployment baseline.
Scope Limitations
Commercial service scheduling excluded.
Business Impact
Technician workloads became more evenly distributed.
What Stayed Human
- Technical diagnostics
- Repair decisions
What We Learned
Technician skill routing was necessary for scheduling accuracy.